Project Name : constructing a main water pipeline for Aqqabba - Tubas
Project Description : construction of transmission pipline with a length of 3,266 meter and 8 inches diameter from Aqqabba pumping station to Aqqabba reservoir as well as constructing five manholes in the region.
Project Category : Water line
Project Goal : The project aims at improving water supplies to the residents in Aqqaba by reducing water loss and increasing quantity of potable water
Beneficiary associations : 9,000 Aqqabba
Cost : $280,574
The sponsor : PWA
Completion rate : 100%
Date : 15/3/2017-18/7/2016
Project Status : completed